Why bare PCBs are taking longer to arrive, and what you can do about it…

We’d rather give you bad news early than bad news late, so here it is.

Bare printed circuit boards (PCBs) from Asia are taking a lot longer to reach us than they did at the start of the year. That’s affecting PCB assembly lead times for electronics manufacturers across the UK, though you might not hear that from every supplier. We thought you should know what’s going on and what it could mean for your builds next year.

Why are bare PCB lead times increasing?

For as long as we’ve been assembling boards, the bare PCB has been the easy bit. You sent us the Gerbers, we ordered the boards and they turned up on time. If anything was going to give us a headache, it was usually a component.

That’s changed this year. Back in March, the German board maker ILFA said standard FR-4 laminate (what most industrial and commercial boards are made from) was taking around four weeks to come through from the big suppliers. It used to be a few days. More specialised laminates were taking up to 140 days.

It’s got tighter since. Nikkei Asia has reported board makers seeing lead times double on a lot of their products, and a few orders being quoted at 30 months. HP and Dell have both said they’re worried about getting enough boards for their 2027 products. If firms that size are struggling, the rest of us will feel it too.

How is AI demand affecting PCB manufacturing?

The short answer is AI, or more accurately the data centres being built to run AI.

The servers in those data centres use very complex boards. Würth Elektronik and STARTEAM Global reckon they have three to five times as many layers as a normal board, and every layer needs laminate, glass-fibre cloth, copper foil and resin. They’re the same raw materials your boards are made from.

On top of that, one square metre of the high-end laminate used in AI hardware takes up about as much production capacity as five square metres of ordinary FR-4, and it sells for a lot more. Laminate makers and board fabricators are understandably putting those orders first. Your boards haven’t changed; they’ve just moved further down the list.

When will PCB material shortages improve?

We don’t expect so, at least not in the short term.

The glass-fibre cloth used in laminate is one of the biggest bottlenecks. Würth and STARTEAM don’t expect much improvement before 2028, and new glass, foil and laminate plants take years to build.

Prices are rising too. Laminate went up by between 20% and 40% in the first half of this year, depending on the grade, and suppliers have put through several increases.

Europe can’t fill the gap. Twenty years ago there were over 600 PCB factories and around 20 laminate makers in Europe. Today there are fewer than 150 board makers and only one laminate producer.

Why are we telling you?

The easy option would be to keep quoting last year’s lead times and sort the delays out as they happen. We don’t work like that. A date that slips at the last minute can cost you production time, a launch date, or goodwill with your own customers. We’d rather you heard it from us now.

How can manufacturers manage longer PCB lead times?

The businesses who come through this best will be the ones who plan a bit further ahead. In practice:

Let us know what’s coming. If you’ve got a rough idea of what you’ll need over the next six to twelve months, tell us. Even a loose forecast means we can book board capacity early instead of ordering when the PO arrives.

Think about scheduled or call-off orders. You commit to a volume and we deliver it in batches, so we can order boards early and you still decide when assemblies ship.

Have another look at board materials. Unusual thicknesses, specialist laminates and high layer counts are the hardest to get hold of right now. If your design doesn’t really need them, standard materials can make a big difference to lead time. We’re happy to go through the designs with you.

Start new products earlier. If something’s due to launch in 2027, talk to us about the boards now, even if the design isn’t finished.

Allow for price changes. Material costs are still moving, so quotes may be valid for shorter periods than you’re used to. Ordering earlier is the easiest way to fix a price.

How is Active EMS managing PCB supply delays?

We’re working with the board suppliers we’ve used for years to book capacity ahead where we can. The lead times we quote are realistic ones, and if anything changes we’ll let you know straight away.

Planning your PCB assembly requirements for 2027?

If you’ve got builds planned for next year, get in touch now and we’ll talk through volumes and board specs.

Email – hello@active-ems.co.uk or speak to your usual contact at Active EMS.